Power Supply to Dammam Housing Project

Project Overview

Bin Omairah’s scope of works under this Project is to perform detailed engineering and design, procure, supply and deliver all equipment and materials to the Worksite, construct, install, test, commission, and put into service the 115 Kv Under Ground cable circuits along the power supply lines to Dammam Housing Projects.

Date

Client

Saudi Electricity Company (SEC)

Contract Type

Scope of Work

Consultant

14
No. Of Circuits
73KM
Route Length
219KM
U/G Cable Length
42KM
Fiber Optic Cable Length
160,000M3
Excavation Work
147,000M3
Backfilling Work
99,000M2
Asphalting Work
1136ML
HDD ( Horizontal Directional Drilling)
687Joint
Insulated Joints
6KM
Road constriction Length
94,918 M3
Road construction Filling
23,901 M3
Road construction Cutting
90 ML
Route below ARAMCO Pipe Lines
22,308 M3
Excavation QTY
21,438 M3
Backfilling Filling Work
850 M3
Concrete Work Below Pipes